Westcote Build Process

PROJECT DETAILS

After the internal strip-out the previous week the diggers were bought in for week 1 of the external demolition.
This week’s main achievements were to set up site facilities, cabins, portable washroom and knock down of the bungalow.

WEEK ONE

After the internal strip-out the previous week the diggers were bought in for week 1 of the external demolition. This week’s main achievements were to set up site facilities, cabins, portable washroom and knock down of the bungalow.

WEEK TWO

Once the bungalow was fully demolished all the rubble had to be cleared out of site.


14th July 2015