Westcote Build Progress

Westcote Build Progress

Week One

After the internal strip-out the previous week the diggers were bought in for week 1 of the external demolition.

This week’s main achievements were to set up site facilities, cabins, portable washroom and knock down of the bungalow.

Westcote Build Progress

Week Two

Once the bungalow was fully demolished all the rubble had to be cleared out of site.

Westcote Build Progress

Week Three

More clearance work started in preparation for the preparation for the foundation. Signage was added.

Westcote Build Progress

Week Four

The foundations are being dug out in preparation for the concrete to be poured in the following week.

Westcote Build Progress

Week Five/Six

Pouring the concrete mix using a large pump.

Westcote Build Progress

Week Seven

Week 7

Westcote Build Progress

Week Eight

We are not above the ground and DPC level!